30 men can complete a job in 40 days. Find the time taken by 25 men to complete the job (in days) (very important for me)
Answers
Answered by
1
Step-by-step explanation:
Job completed by one man in days=30×40=120days
Then job completed by 25 men =25×120=3000days
Answered by
1
Answer:
33.33
Step-by-step explanation:
30:40::25:x
=product of means = product of extreme
30x = 40 × 25
x = (40 × 25) /30
x = 33.33 is your answer.......
hope it helps you....
mark me as brainliest....