30 men can complete a job in 40 days. Find the time taken by 25 men to complice the job (in days)​

Answers

Answered by manu062jat
2

Answer:

48

Step-by-step explanation:

30×40=25×D

1200=25×D

D=1200÷25

D=48

THEN 25 men complete this job in 48 days