Answered by Theultimatehero20
10
Let amount of work = x
x/30men = 40days
x = 30 x 40 = 1200

At 24days, amount of work completed is
24/40 x 1200 = 720

Amount of work remaining = 1200-720=480

480/no of men remaining = 40days
no of men = 480/40=12 men

No of men that left = 30-12=18men

Option B [Answer]