30 men can complete the job in 40 day .in how many days 25 men complete the job​

Answers

Answered by Anonymous
2

Answer:

Mark me as brainlist

Step-by-step explanation:

Always go step by step for easily understanding.

30 men —40 days

1 man - 40*30 days=1200 days

25 men=1200/25 days

=48 days

So 25 men require 48 days to complete that job.