30 men can dig a well in 4 days .How many more men is needed to dig the same well in 3 days?
Answers
Answered by
1
Explanation:
ok i can try to answer it:
4 day need to dig a well by 30 men
1 day need to dig a well by 30×4 men
3 day need to dig a well by 30×4/3
=40.
:: The answer is 40 men need to dig a well in 3 day