30 men can do a piece of work in 12 days. in how many days 9 men can do the same work
Answers
Answered by
1
40 days.
Step-by-step explanation:
30 men can do 1 work in 12 days.
1 man can do 1 work in 12 × 30 days.
9 men can do 1 work in 12 × 30/9 days =
40 days