30 men can do a piece of work in 12 days. in how many days 9 men can do the same work

Answers

Answered by MrBrainlyBrilliant
1

40 days.

Step-by-step explanation:

30 men can do 1 work in 12 days.

1 man can do 1 work in 12 × 30 days.

9 men can do 1 work in 12 × 30/9 days =

40 days