30 men can do a piece of work in 16 days , in how many days 8 men can do the same work
A) 30 Days
B) 40 Days
C) 50 Days
D) 60 Days
Answers
Answered by
3
Answer:
30×16=8×x
x=60 days
Step-by-step explanation:
inverse proportion