30 men take 10 day to build a wall .25 men take how many days to build a wall.
Answers
Answered by
7
Answer:
Time taken by 30 men = 10 day
time taken by 1 men = 10/30= 1/3 days
Time taken ny 25 men = 1/3 x 25 = 25/3= 8.3 days
Hope it helps you