30 men working 16 hours per day make a house in 10 days in how many days will 24 men working 18 hours per day to make it
Answers
Answered by
0
Number of man hours required to complete the work is 30x16x10 = 4800 man hours.
Let the number of days taken be X. Then
24x18X = 4800
Or, X = 4800/(24x18)
Or, X = 100/9
Or, X=11.11
Hence,work will be completed on the 12th day.
hope it will help....☺️
Let the number of days taken be X. Then
24x18X = 4800
Or, X = 4800/(24x18)
Or, X = 100/9
Or, X=11.11
Hence,work will be completed on the 12th day.
hope it will help....☺️