30 people can complete a work in 12 days. how many will20 people take for completing the same work
Answers
Answered by
1
If 30 people can complete the work in 12 days.
Then 1 man will complete the work in (30×12)days.
Then 20 men will complete the work in (30×12/20)days = 18days.
Answered by
0
30÷12=5_2×20=2is answer
I hope it helps u