30 people can reap a field in 17 days.
(1) How many people will be needed to reap the same field in 10 days?
(ii
) How many people will be needed to reap a field that is double the size of the
original field in 10 days?
answer of 2 part...
plz fast....
Answers
Answered by
2
Answer:
Total Mandays = Total people X number of days = 30X17 510 Mandays
Total people required to reap in 10days =510/10 = 51
People required to reap the double the size of field in 10days = 51X 2 = 102 people