30 persons can finish a task in 17 days. How many more persons should be engaged to complete the same task in 10 days?
Answers
Answered by
0
Answer:
By cross multiplication
30-17
?-10
Let ? be X
17x=30*10=300/17
X=17 persons
PLEASE MARK ME AS BRAINLIEST