30 persons can repair a road in 13 days working 6 hours a day in how many days can 39 muscles working 5 hours a day complete the work
Answers
Answered by
5
Answer:
❤️ Hey, Mate ❤️
If 30 person works 6 hr and time take =13 days
if 1 men work 6 hr then he will take =13×30
=390
if 39 men work 6hr then he will take=390/39
=10
if 39 men work 1hr then he will take=10×6
=60
if 39 men work 5 hr then he will take=60/5
=12
hope this helps u ❤️