30 workers can dig a pond in 12 days. How many days will it take 16 workers to dig the same pond.

Answers

Answered by harshita39002
2
hope it will help you
Attachments:
Answered by sakshii8080
0

As per the data given in the above question.

In the above question it is given that,

The given data is 30 workers can dig a pond in 12 days,

We have to find how many days will it take 16 workers to dig the same pond.

Thus, solving the equation we get,

Let the required worker be x,

30\times 12=x\times 16\\360=16x\\x=\frac{360}{16}\\x=22.5

Hence required 22.5 days or 23 days.