Math, asked by akae5004, 1 year ago

30 workers can dig a trench in 5 days . how many workers will be required to dig in 6 days

Answers

Answered by Siddharta7
5

M1 × D1= M2 ×D2

30×5= M2×6

M2= (30×5)/6=25 workers