Math, asked by Vaibhav950, 1 year ago

30 workers can dig a trench in 5 days .How many workers will be required to dig it in 6 days

Answers

Answered by desiboyz3
35
M1 × D1= M2 ×D2
30×5= M2×6
M2= (30×5)/6=25 workers will be the answer

Vaibhav950: Extremely thanks to you
desiboyz3: welcome
Vaibhav950: :-)
Answered by Siddharta7
16

M1 × D1= M2 ×D2

30×5= M2×6

M2= (30×5)/6=25 workers.