30 workers can dig a trench in 5 days .How many workers will be required to dig it in 6 days
Answers
Answered by
35
M1 × D1= M2 ×D2
30×5= M2×6
M2= (30×5)/6=25 workers will be the answer
30×5= M2×6
M2= (30×5)/6=25 workers will be the answer
Vaibhav950:
Extremely thanks to you
Answered by
16
M1 × D1= M2 ×D2
30×5= M2×6
M2= (30×5)/6=25 workers.