Math, asked by vrathan, 1 year ago

30 workers can dig a trench in five days .how many workers will be recquired to dig it in 6 days

Answers

Answered by mani762
3

M1* D1=M2*D2

30*5=M2*6

M2=(30*5)/6=25 workers will be the answer


mani762: please mark it as the brainliest if it helps you