Math, asked by muhammadalihamd, 6 months ago

30 workers complete a work in 50 days work 10 hours a day. Find in how many days 25 workers complete this work, working 12 hours a day.

Answers

Answered by eliteslasher96
4

Step-by-step explanation:

no. of hours to do the work = 30 × 10 × 50 hours

or, = 15000 hours

now, no. of workers = 25

no. of working hours per man per day = 12 hours

no. of days needed to complete the work = 15000/(25 × 12)

or, = 15000/300

or, = 50 days

hence, they will take 50 days too.

hope this will help you