30men repair a road in 56 days by working 6 hour daily. In how many days 45 men well repair road by working 7 hours daily?

Answers

Answered by apurbamandal794
13

30 men do a work in 1hr=1/(56*6)

1 men do a work in 1hr=1/(56*6*30)

45 men do a work in 1hr=45/(56*6*30)

45 men do a work in7hr=(7*45)/(56*6*30)

=1/32

then 45 men repair a road in 32 days by working 7 hrs daily,,,

if u don't understand this write me!!!