32 men are working on a project for 7 hours a day. They take 40 days to complete the
project. Now, assume that only 20 men are available for working 8 hours a day. In
how many days will these 20 men complete the work?
Answers
Answered by
3
Answer:
working hour required for finish the work is
=32×7×40=8960 hours
so when 20 men working 8 hour per day
20×8=160 hour working per day
working hour required for finish the work is 8960
then 20 men working 8 hour per day they complete the work in 8960/160=56 days
Answered by
1
The number of days to be taken to complete the same piece of work is 56 days.
32 men are working on a project for 7 hours a day. They take 40 days to complete the project. Now, assume that only 20 men are available for working 8 hours a day.
We have to find the number of days to be taken by 20 men to complete the same work.
It can be solved using formula, N₁D₁H₁ = N₂D₂H₂
Where
- N indicates number of workers
- D indicates number of days
- H indicates the work done in hours per day
Here, N₁ = 32 , D₁ = 40 , H = 7 , N₂ = 20 , H₂ = 8
⇒ 32 × 40 × 7 = 20 × D₂ × 8
⇒ D₂ = 56 days
Therefore the number of days to be taken to complete the same piece of work is 56 days.
Similar questions