32 men can complete a project in 70 days and 40 women can complete the same project in 72 days. 20 men started working and after one fourth of the work was completed, they were replaced by 48 women. In how many days was the whole project completed?
Answers
Answered by
0
jufjbfslcscfds cshjcvlsbxs.
Answered by
3
Answer:
73 days
Step-by-step explanation:
32 men can complete a project in 70 days
1 men can complete whole work in days =
20 man can complete whole work in days =
20 man can complete part of work in days =
Remaining work =
20 men started working and after one fourth of the work was completed, they were replaced by 48 women.
40 women can complete the same project in 72 days.
1 women can complete the same project in days. =
48 women can complete the same project in days. =
48 women can complete part of work in days. =
So, remaining work will be completed in 45 days
And total work completed in days = 28+45 = 73 days
Hence the whole project was completed in 73 days.
Similar questions