Math, asked by sriramchiluveru122, 3 months ago

32 Men can do a piece of work in 12 days. In how many days 8 men can do the same work? *​

Answers

Answered by mamtamailstar
0

Answer:

ok tsilmhgvbbkknj wd2wf2rg

Answered by Anonymous
0

Answer:

32 Men can do a piece of work in 12 days. In how many days 8 men can do the same work? *

Step-by-step explanation:

Solution-

If 32 men do a work in 12 days 8 men?,

first divide like me 32÷8= 4 men

then do 4×12= 48

8 men can do a piece of work in 48 days