32 men can do a work in 8 hours 36 minutes how long will it take for 48 men to complete it​

Answers

Answered by r57611614gmailcom
1

Answer:

I hope this pic will help you please fellow me

Attachments:
Answered by gfan2962
2

Answer:

344 minutes

Step-by-step explanation:

  1. 32 men do work in 8 hours 36 mins=516 mins

1 men do it in = 32 × 516 = 16512 mins

  • 48 men do it = 16512÷48=344 mine