32 persons can do a piece of workin 20 days. How many more people are required to complete the work in 16 days?
Answers
Answered by
0
Please see the attachment
Attachments:
Answered by
1
according to question,
32 persons can do a piece of work in 20 days
so, in a day to complete the work , number of people are required = 20 × 32 = 640
so, in 16 days to complete the work , number of people are required = 640/16 = 40
hence, 40 people are required to complete the work in 16 days .
32 persons can do a piece of work in 20 days
so, in a day to complete the work , number of people are required = 20 × 32 = 640
so, in 16 days to complete the work , number of people are required = 640/16 = 40
hence, 40 people are required to complete the work in 16 days .