32 workers can complete a work in 84 days . How many workers can complete it in 48 days
Answers
Answered by
1
Answer:
i hope ur ans is 50........
Answered by
1
Answer:
- 56 Workers
Explanation:
- There is inverse relation between man & work, if man increases, work decreases
- Same happens in time, speed, distance questions as well
- Only ratio matters, so 84:48 = 7:4
- This ratio will become inversed so, 7X32/4=56