327. 56 labourers can harvest a field in 8 days.
How many more labourers are required to
harvest the field in 7 days?
(A) 7 labourers (B) 16 labourers
(C) 10 labourers (D) 8 labourers.
Answers
Answered by
3
Answer:
inverse variation question
7*x=56*8
x=56*8/7
x=64
more labourers=64-56=8
Answered by
3
Answer:
x = 8
And, number of labours required to harvest the field in
7 days is 8
Also, option D (8 labours) is the correct answer
Step-by-step explanation:
→ Let, the number of workers required to harvest the
field in 7 days = x
→ According to the Question,
→ Number of labours Number of days
56 8
x 7
→ This is a type of inverse variation/Proportion
→ Therefore, 7x = 56 × 8
→ x = 56 × 8 / 7
→ x = 8 × 8
→ x = 64
→ Also, more labours = 64 - 56
= 8
→ Thus, the number of labours required to harvest the
field in 7 days is 8
Please mark me as the Brainliest answer
Similar questions
History,
1 month ago
English,
1 month ago
Computer Science,
10 months ago
English,
10 months ago
English,
10 months ago