33 men can complete a work in some days and 24 men can do the same work in 6 days more in how many days the work can be completed by 44 men
Answers
Answered by
5
let ,
33 mens can do the work in "x" days
24 men can do the work in " x + 6 " daysb
than,
33x = 24( x + 6)
33x = 24x + 198
x = 16 days
Now,
33 men can do work in 16 days
1 man can do work in 16/33
44 men can do work in 16/33 *44= 12 days
muhammadsohaibansar2:
how 16*44/33 = 12???
Answered by
4
Step-by-step explanation:
33 men complete their work in some days,
so,
we can write
33 M = S days
Similarly,
24 M = 6 days
and
44 M = x days
now,
24 M = 6 days
1 M = 6/24 days
1 M = 1/4 days
now multiply by 44 on both sides
then,
44 M = 44/4 days
44 M = 11 days,
we can say that, 44 men will take 11 days to complete work.