Math, asked by rabirno49, 5 months ago

33. P is twice as efficient as Q and
together they finish a piece of
work in 12 days. How many
days will P take to complete the
work alone?​

Answers

Answered by Itzraisingstar
16

\huge\fcolorbox{black}{lime}{AnsweR:}

18 days.

Step-by-step explanation:

Together they complete the work in 12 days ,

So, in one day they complete 1/12work.

Since P is twice good as Q,

So P's work done in one day= 2x ,

& Qs work done in one day= x ,

So, 2x + x = 1/12,

3x = 1/12,

X = 1/36,

So, Qs work done in oneday= 1/36,

& P's work done in one day= 1/18,

So, P alone will take 18 days to complete a piece of work ,

Answered by Anonymous
2

Answer:

18 days.

Step-by-step explanation:

Together they complete the work in 12 days ,

So, in one day they complete 1/12work.

Since P is twice good as Q,

So P's work done in one day= 2x ,

& Qs work done in one day= x ,

So, 2x + x = 1/12,

3x = 1/12,

X = 1/36,

So, Qs work done in oneday= 1/36,

& P's work done in one day= 1/18,

So, P alone will take 18 days to complete a piece of work ,

Similar questions