33. P is twice as efficient as Q and
together they finish a piece of
work in 12 days. How many
days will P take to complete the
work alone?
Answers
Answered by
16
18 days.
Step-by-step explanation:
Together they complete the work in 12 days ,
So, in one day they complete 1/12work.
Since P is twice good as Q,
So P's work done in one day= 2x ,
& Qs work done in one day= x ,
So, 2x + x = 1/12,
3x = 1/12,
X = 1/36,
So, Qs work done in oneday= 1/36,
& P's work done in one day= 1/18,
So, P alone will take 18 days to complete a piece of work ,
Answered by
2
Answer:
18 days.
Step-by-step explanation:
Together they complete the work in 12 days ,
So, in one day they complete 1/12work.
Since P is twice good as Q,
So P's work done in one day= 2x ,
& Qs work done in one day= x ,
So, 2x + x = 1/12,
3x = 1/12,
X = 1/36,
So, Qs work done in oneday= 1/36,
& P's work done in one day= 1/18,
So, P alone will take 18 days to complete a piece of work ,
Similar questions