34. If 18 labours take 15 days to complete one task, then how many days
6 labours need to complete the same task?
(1) 3 days
(2) 90 days
(4) 45 days
(3) 5 days
Answers
Answered by
0
Answer:
correct answer is 45 days
MARK ME AS BRAINLIEST
Answered by
7
Six labours will take 45 days to complete the task
Days taken by 18 labours to complete the task = 15 days. (Given)
Thus,
Total man days needed to complete the task
= 18 × 15
= 270 mandays
Now, time taken by 6 labours to complete the task -
= 270/6
= 45
Thus 6 labours will take 45 days to complete the task.