35. 12 persons can finish a piece of work in 8 days. How many persons can
finish the same work in 4 days?
Answers
Answered by
0
Answer:
6 workers if we go with unitary method bt the answer is nt 6 is we go logically
Answered by
0
Answer:
8 people complete work in 6 days
12 people complete in how many days?
Increase in people implies decrease in number of days.
Number of men increase by 12/8 agreed?
So number of days decrease by (8/12) x 6 = 4
Hence work can be done in 4 days.
Thank you.