35 men can do a piece of work in 24 days . How many men will be required to complete the same work in 15 days ?
Answers
Answered by
0
Answer:
56
Step-by-step explanation:
We have, 35 men took 24 days to complete the work
Hence, Number of men needed to complete the work in 1 day = 35 × 24 = 840
Hence, to complete the work in 15 days = 840 ÷ 15 = 56
So, 56 men are needed to complete the work in 15 days.