Math, asked by lilybora28, 2 months ago

35 men can do a piece of work in 24 days . How many men will be required to complete the same work in 15 days ?

Answers

Answered by duttashrabani7
0

Answer:

56

Step-by-step explanation:

We have, 35 men took 24 days to complete the work

Hence, Number of men needed to complete the work in 1 day = 35 × 24 = 840

Hence, to complete the work in 15 days = 840 ÷ 15 = 56

So, 56 men are needed to complete the work in 15 days.