35 men do a Piece of work in 20 days how much days will 25 men take to finish the same work
Answers
Answered by
0
Answer:
1 men =20/35
20men= 20/35×25
Answered by
1
Answer:
28 days
Step-by-step explanation:
35 men --> 20 Days
1 men --> 35 * 20
25 men --> 35 * 20 / 25
35 * 20 / 25
7 * 20 / 5
7 * 4 = 28 days