Math, asked by adityabrv4655, 1 year ago

35 persons are engaged to complete a work in 60 days. after 32 days it is observed that only (2/5)th part of the work has been done. the number of persons to be engaged to complete the remaining work in the said period is

Answers

Answered by Anusree1231
1
Now 25 persons to be engaged to complete the remaining work inthe said period
Answered by pinquancaro
0

Answer:

The number of persons to be engaged to complete the remaining work in the said period is 60.

Step-by-step explanation:

Given : 35 persons are engaged to complete a work in 60 days. After 32 days it is observed that only (2/5)th part of the work has been done.

To find : The number of persons to be engaged to complete the remaining work in the said period is ?

Solution :                        

Let N_1=35 be the number of persons are engaged to complete a work in 60 days.

Let N_2 be the number of persons to be engaged to complete the remaining work.

After 32 days it is observed that only (2/5)th part of the work has been done.

i.e. Work done is W_1=\frac{2}{5} and D_1=32

Remaining days = 60-32=28 days do work done 1-\frac{2}{5}=\frac{3}{5}

i.e. Work done is W_2=\frac{3}{5} and D_2=28

According to question the formula given is

\frac{N_1\times D_1}{W_1}=\frac{N_2\times D_2}{W_2}

\frac{35\times 32}{\frac{2}{5}}=\frac{N_2\times 28}{\frac{3}{5}}

2800=\frac{N_2\times140}{3}

N_2=\frac{2800\times 3}{140}

N_2=60

Therefore, The number of persons to be engaged to complete the remaining work in the said period is 60.

Similar questions