35 persons are engaged to complete a work in 60 days. after 32 days it is observed that only (2/5)th part of the work has been done. the number of persons to be engaged to complete the remaining work in the said period is
Answers
Answer:
The number of persons to be engaged to complete the remaining work in the said period is 60.
Step-by-step explanation:
Given : 35 persons are engaged to complete a work in 60 days. After 32 days it is observed that only (2/5)th part of the work has been done.
To find : The number of persons to be engaged to complete the remaining work in the said period is ?
Solution :
Let be the number of persons are engaged to complete a work in 60 days.
Let be the number of persons to be engaged to complete the remaining work.
After 32 days it is observed that only (2/5)th part of the work has been done.
i.e. Work done is and
Remaining days = 60-32=28 days do work done
i.e. Work done is and
According to question the formula given is
Therefore, The number of persons to be engaged to complete the remaining work in the said period is 60.