35 workers are employed to complete a construction project in 16 days. Before the project starts, the boss of the company is told that he needs to complete the project in 14 days. Assuming that all the workers work at the same rate, how many more workers does he need to employ in order to complete the project on time?

Answers

Answered by hcps00
6

Step-by-step explanation:

115⋅60(15+w)⋅36w=1=10 more workers

=================================================================

To view the LATEX source click '⋯' → Suggest Edits

ANSWER

By inverse proportion,

28×x=35×16

x=

28

35×16

=20 days