Statement of the given problem,
(i) 35 workers complete a project in 16 days. The boss of the company is told that he needs to complete the project in 14 days. How many more workers does he need to employ in order to complete the project on time?
(ii) Let N denotes the number of more workers needed to be employed in order to complete the project on time.
We now that time (t) required to complete a project is inversely proportional to the number (n) of workers.
Hence we get following condition,
t ∝ 1/n or t*n = constant …. (1)
Therefore from (i), (ii) & (1) we get following relation,
(N + 35)*14 = 35*16
or N + 35 = 40 or N = 5 [Ans]