Math, asked by syedmohammadbilal6, 1 month ago

35 workers are
employed to complete the construction project in 16 days before the project are the birth of the company's told that he needs to complete the project in 14 days during that the all work of work at the same rate how many more what does he need to apply in order to complete the project on time​

Answers

Answered by satvik6497
2

Answer:

SOORY BUT I CANT UNDERSTAND YOUR QUESTION

Step-by-step explanation:

SORRY

Answered by aastha1260
1

Answer:

5

Step-by-step explanation:

Statement of the given problem,

(i) 35 workers complete a project in 16 days. The boss of the company is told that he needs to complete the project in 14 days. How many more workers does he need to employ in order to complete the project on time?

(ii) Let N denotes the number of more workers needed to be employed in order to complete the project on time.

We now that time (t) required to complete a project is inversely proportional to the number (n) of workers.

Hence we get following condition,

t ∝ 1/n or t*n = constant …. (1)

Therefore from (i), (ii) & (1) we get following relation,

(N + 35)*14 = 35*16

or N + 35 = 40 or N = 5 [Ans]