36 boys can do a piece of of work in 49 days how many extra boys should be engaged so that the work may be finish in 21 day
Answers
Answered by
1
Answer:
48 boys
Step-by-step explanation:
step 1
work out the total number of days to complete the piece of work. Each boy worked 49 days and there were 36 boys
Days*Boys = total number of days
49*36= 1764
so it took total of 1764 days to complete the piece of work
step2
days*boys = total number of days
we get
21*boys= 1764
boys = 1764/21= 84
so 84 boys needed to finished a piece of work in 21 days
step 3
84-36=48
48 extra boys are required to complete the piece of work