Math, asked by tiwari2308, 1 year ago

36 MEN CAN COMPLETE A PIECE OF WORK IN 20 DAYS. IN HOW MANY DAYS WILL THE WORK BE COMPLETED IF THE MEN IS REDUCED TO 12.

Answers

Answered by abhi178
9

36 men can complete a piece of work in 20 days.

in how many days will the work to be completed if the men is reduced to 12.

solution : 36 men can complete a piece of work in 20 days.

so 1 men can complete the piece of work in 36 × 20 = 720 days

so 12 men can complete the piece of work in 720/12 = 60 days

Therefore 12 men can complete the same work in 60 days.

you can solve it using formula, M₁D₁ = M₂D₂

here M indicates no of men and D indicates no of days required to complete the work.

here M₁ = 36 , D₁ = 20 , M₂ = 12

so, 36 × 20 = 12 × D₂

⇒D₂ = 60 days

Therefore in 60 days, 12 men complete the work.

Answered by Munalini2007
2

Answer:

Answer is 60days

Step-by-step explanation:

36 men can complete the piece of work in = 29days

*1 men can complete the piece of work in =36x20=720 days

*12 men can complete the piece of work in=720/12=60 days

.:.12 men can complete the piece of work in 60 dyas