36 men can complete a piece of work in 21 days. In how many days will 12 men finish it ?
Answers
Answered by
0
Answer:
Given, 36 men can finish a piece of work in 25 days
=> The number of man-days = 36*25 = 900
Let x be the number of days taken by the 15 men to do the piece of work
=> The number of man-days = 15x
But the number of man-days remains constant.
=> 15x = 900
x = 900/15 = 60
=> 15 men take 60 days to complete the piece of work.
Answered by
10
Answer:
Solution:
36 men can complete a piece of work in 20 days.
So, 1 men can complete the piece of work in 36×20 = 720 days.
So, 12 men can complete the piece of work in 720/ 12 = 60 days.
Therefore in 60 days, 12 men complete the work.