36 men can complete a piece of work in18 days .In how many days will 27 men complete same work
Answers
Answered by
0
Answer:
Step-by-step explanation:
completedreamer:
where is the explanation
Answered by
0
YOUR ANSWER....
LET NO OF DAYS BE x
RATIO OF MEN AND DAYS PROPORTIONAL TO RATIO OF MEN AND DAYS
36:18::27:x
PRODUCT OF EXTREME=PRODUCT OF MEANS
36x=18*27
x=18*27/36
x=13.5 days
HOPE IT HELPS...
MARK AS BRAINIEST ❤
PLZ..PLZ..PLZ..
LET NO OF DAYS BE x
RATIO OF MEN AND DAYS PROPORTIONAL TO RATIO OF MEN AND DAYS
36:18::27:x
PRODUCT OF EXTREME=PRODUCT OF MEANS
36x=18*27
x=18*27/36
x=13.5 days
HOPE IT HELPS...
MARK AS BRAINIEST ❤
PLZ..PLZ..PLZ..