36 men can construct abridge in 18 days. In how many days will 27 men complete the construction?

Answers

Answered by aspirbyed121
2

Answer:

13days and 12hours

Step-by-step explanation:

work done by one man(18 days)=18/36

work done by one man(x days)=x/27

work done by one man in 27days=

work done by one man in x days

=>18/36=x/27

=>18*27=x*36

=>486=36x

=>x=486/36

=>x=13.5

Therefore, no of days =13days and 12hours