36 men can do a pice of work in 7 days How many men will do the same work in 42 days​

Answers

Answered by Anonymous
8

Answer:

Answer:That means 1 men can do the work in 36×7 days, Now we need to determine the number of men to complete the work in 42 days. Therefore, Hence, 6 men can do the same work in 42 days.

Answered by aaronfinny7
1

Step-by-step explanation:

unitory method

men. days

36 7

? 42

?= 7*36/42

ans 6