36 men can do a piece of work in 12 days, how long will 6 men take to do it.

Answers

Answered by nitingans
0

Answer:

Step-by-step explanation:

If 36 men can do a piece of work in 12 days,

6 men can do it in

(12*36)/6 days = 72 days