36 men can do a piece of work in 12 days. In how many days 9 men can do the
same work?
7.
Men
Days
36
Answers
Answered by
1
Answer:
48 days
Step-by-step explanation:
36 men=12 days
so
1 man =36×12 days
9 men=36×12/9
=48 days