Math, asked by varshayadavalli20, 2 days ago

36 men can do a piece of work in 12 days. In how many days 9 men can do same work?​

Answers

Answered by prachibarapatre
2

Answer:

9 men will require 48 days to complete the work

Step-by-step explanation:

Here it is given that 36 men can do a piece of work in 12 days

We have to find out the number of days taken by 9 men to do the same work

Let us assume the number of days to be x

We will use inverse proportion because as the number of men decrease, the number of days taken increases

days taken by 36 men = 12

days taken by 9 men = x

9x = 36 × 12

9x = 432

x = 432/9

x = 48

Answered by Swastikook
3

Answer:

The answer will be 48

hope it will correct

Similar questions