36 men can do a piece of work in 12 days.in how many days 9 men can do the same work?

Answers

Answered by AJThe123456
3
Heyy mate ❤✌✌❤

Here's your Answer ......

⤵️⤵️⤵️⤵️⤵️⤵️

By using the formula,

M1 × D1 = D2 × M2

=> 36 x 12 = 9 x D2 

=> D2=48 

Therefore, they require 48 days.
✔✔
Answered by fanbruhh
6
hey

here is answer

given

36 men can do a piece of work in 12 days

to find

number of days in 9 men can do a work.


according to question



D1*M1=D2*M2

= 36*12=D2*9.


432=D2*9


D2=432/9

no of days=48

hope it helps

thanks