36 men can do a piece of work in 12days in how many days 9 men can do the camp how long will the stock last
Answers
Answered by
5
Step-by-step explanation:
this is a inverse proportion question
36men=12 days
9men=x days
inverse proportion question we do
36×12=9×x
x=36×12/9
x=4×12=48 days