Math, asked by abhiramreddygutha9, 1 month ago

36 men can do piece of work in 12 days how many days 24 men can do same work​

Answers

Answered by kumaratal59
1

Answer:

good morning friend

have a great day

Answered by realxgaming5432
1

Answer:

Correct option is

A

48

No. of men working α

no.ofworkdays

1

∴N= no. of men working

D= no. of workdays

∴Nα

D

1

⇒N=

D

K

where K is constant

∴N

1

=36men,D

1

=12days

∴K=N

1

D

1

=36×12=432

∴ N

2

=9men⇒D

2

=

N−2

K

=

9

432

=48days

Step-by-step explanation:

hope you liked the answer

Similar questions