36 mens can complete a piece of work in 18 days . in how many days will 27 men complete the same work
Answers
Answered by
1
Step-by-step explanation:
mark me as a BRAINELIST plz
Attachments:
Answered by
5
Step-by-step explanation:
Let the no. of days = x
Less men more days indirect proportion :
27×X = 36×18
36×18/27
x = 24
no. of days : 24 days