360 men were about to complete a peice of work in 15 days some workers were absent remaining people completed the work in 27 days how many people were absent​

Answers

Answered by pkchandni403
0

Answer:

360 men will complete a work in in 15 days

1 man will complete the work in in = 360*15 days

The people who were used to complete the work in 27 days =360*15/27

=5400/27

=200 men

. ' . The number of people who were absent =360-200