360 workers can finish a construction work in 60 days. how many more workers should be added to complete the same work in 45 days ?​

Answers

Answered by subbaraojv129
2

Answer:

360 workers > finished in 60 days

> finished in 40 days

THE NO OF WORKERS = 360×60÷45

=480 workers